Most small contractors think about cash flow in terms of what clients owe them. Retainage, slow pay apps, and deposits get all the attention. The other side of the equation gets less: what you owe your suppliers, and when you owe it. Your account at the lumber yard, electrical supply house, or plumbing wholesaler is a short-term, interest-free loan. Handled well, it closes the gap between buying materials and getting paid for the work. Handled badly, it turns into late fees, frozen accounts, and a supplier lien on your client's house.
This guide covers how supplier credit terms work, how to work out whether an early-payment discount is worth taking, and the systems that keep supplier bills from eating your margin.
Reading Supplier Terms: What “2/10 Net 30” Means
Supplier invoices and credit applications use shorthand that's easy to skim past. Each format means something different for your cash:
- Net 30 — The full balance is due 30 days from the invoice date. Some suppliers count from the statement date instead, which can give you up to 60 days. Read your credit agreement to find out which one applies.
- 2/10 Net 30 — Take 2% off if you pay within 10 days. Otherwise the full amount is due at 30 days.
- Net 10th Prox — Everything bought this month is due on the 10th of next month. Common at lumber yards. Buy on the 1st and you get about 40 days. Buy on the 31st and you get 10.
- 2% 10th Prox, Net 25th — 2% off if you pay by the 10th of the following month, full balance due by the 25th.
- 1.5% per month service charge — The late fee. It works out to 18% a year, which is more than most credit cards charge business customers.
Billing timing matters more than most contractors realize. If your account bills on prox terms, putting big material orders early in the month gets you the most float. A $12,000 framing package delivered on the 2nd gives you over five weeks before payment is due. The same package delivered on the 29th gives you less than two weeks.
The Math on Early-Pay Discounts
A 2% discount sounds small. It isn't. When you take 2/10 net 30, you're paying 20 days early in exchange for 2% off. Annualized, that's roughly a 37% return on the cash you used:
- 2/10 net 30 — (2 ÷ 98) × (365 ÷ 20) = about 37.2% annualized
- 1/10 net 30 — (1 ÷ 99) × (365 ÷ 20) = about 18.4% annualized
- 2% 10th prox, net 25th — (2 ÷ 98) × (365 ÷ 15) = about 49.7% annualized
In dollars: a contractor buying $40,000 a month in materials on 2/10 terms leaves $800 a month on the table by paying at day 30. That's $9,600 a year. For a small remodeler netting $90,000, it's more than 10% of profit, given up for doing nothing.
If you have a business line of credit at 9–12% and you aren't using it to capture 2/10 discounts, you're turning down one of the best trades available to you. Borrowing at 10% to earn 37% is an easy decision.
There's one condition. Only take the discount if paying early doesn't leave you short on payroll, taxes, or sub payments over the next two weeks. A discount isn't worth a missed payroll. Check your cash forecast first. If the next 14 days are tight, pay at net 30 and keep the cash.
Opening Accounts Without Signing Away Your House
Most supplier credit applications include a personal guarantee, even when you operate as an LLC or corporation. That clause makes you personally liable for the account balance if the business can't pay. Many contractors sign it without reading it. Before you do:
- Ask to strike or cap the guarantee. Established suppliers will often remove it after 12–24 months of on-time payment, or limit it to a dollar amount equal to your credit limit. You have to ask.
- Check the venue and attorney fee clauses. Some applications require you to pay the supplier's collection costs and to litigate in their home county, which may be three hours away.
- Watch for spousal signature lines. If your spouse isn't involved in the business, they shouldn't be guaranteeing your lumber bill.
- Request a credit limit that fits your largest job. A $10,000 limit is a problem when one framing package runs $18,000. Ask for a limit equal to about 1.5 times your largest expected monthly material spend.
Open accounts at two or three suppliers in each major trade category. One account leaves you exposed to price increases and stockouts. Five accounts means five statements to reconcile and less buying power at each one. Two or three is the right number.
Tie Every Supplier Invoice to a Job
This is where most small contractors lose money without noticing. A supplier statement shows up with 23 line items across six jobs, all mixed together. You pay it and move on. Three months later you can't explain why the Henderson kitchen came in $2,400 over budget.
Fix it at the counter, not at month-end:
- Use job names or PO numbers on every ticket. Most supply houses have a PO or job field. Tell your crew that no ticket leaves the counter without a job name on it.
- Set up separate job accounts for large projects. Many suppliers will open a sub-account for a single job. Statements then arrive already sorted, and lien paperwork stays cleaner.
- Log material costs against the job the day they're bought. Waiting until the statement arrives means reconstructing three-week-old receipts from memory. A tool like TrestleBook lets you enter the expense against the right job from the truck, even without cell service, so your job cost report stays current.
- Reconcile the statement against your logged costs monthly. Every line on the supplier statement should match a cost you've already recorded. Anything that doesn't match is either a missing entry or a supplier error.
Supplier billing errors are more common than most contractors think. Duplicate tickets, wrong pricing tiers, and returns never credited can add up to 1–3% of annual material spend. You only catch them if you reconcile.
Ready to put this into practice? Download TrestleBook Free — it’s free and works offline.
Returns, Credits, and Pricing Tiers
Two leaks that sit on your supplier account without anyone noticing:
Uncredited returns. You over-order drywall by 20 sheets, send it back, and the credit never shows up. Or it shows up as an open credit memo that never gets applied to an invoice. Keep a simple returns log with the date, job, items, and return ticket number, and check it against each statement. Open credits older than 60 days should get a phone call.
Pricing tier drift. Contractor pricing is usually tiered by volume. When you sign up, the supplier quotes you a tier. Over time, special-order items, new SKUs, and counter staff mistakes push some purchases to retail or a lower tier. Twice a year, pull ten common items from your recent invoices and compare them to your agreed price sheet. If you've grown since you opened the account, ask for a tier review. A supplier who gets $300,000 a year from you should be pricing you differently than when you were spending $60,000.
- Ask about restocking fees up front — 15–25% is common on special orders. Build that into how much you order.
- Request quotes in writing for orders over $5,000 — and check the invoice against the quote before paying.
- Negotiate freight and delivery — delivery fees of $75–$150 per drop add up quickly on a job with eight deliveries. Combine orders where you can.
Supplier Lien Rights and Joint Checks
In most states, your suppliers have lien rights on the property where their materials were installed, even though their contract is with you and not the owner. If you don't pay the lumber yard, the lumber yard can put a lien on your client's home. Nothing damages a client relationship faster.
Many suppliers send a preliminary notice (also called a notice to owner or notice of furnishing) at the start of a job to preserve those rights. Clients who get one often call in a panic. Get ahead of it: tell clients during the contract meeting that they may receive notices from suppliers, that it's routine, and that you'll provide lien releases as you pay.
On larger jobs, or when a supplier is nervous about your credit, a joint check agreement can help. The owner or GC issues a check payable to both you and the supplier for the materials portion. The supplier gets security, you get the materials, and the owner gets assurance there won't be a lien. Joint checks slow down your access to the cash, so treat them as a tool for particular jobs, not standard practice.
The rule that prevents most supplier lien problems: pay suppliers from the draw for the job that used the materials. Using the Johnson deposit to pay down the Martinez materials is how contractors end up underwater on three jobs at once.
Building a Monthly Supplier Payment Routine
Keeping a supplier account healthy doesn't take much time, but it does take a routine. A schedule that works for most small contractors:
- Weekly (15 minutes): Enter any material tickets that haven't been logged against a job yet. Flag any invoices with discount deadlines in the next seven days.
- By the 5th of each month: Download or collect all supplier statements. Reconcile each one against your logged job costs and returns log.
- By the 8th: Check your cash forecast. Decide which statements to pay early for the discount and which to pay at net.
- By the 10th: Pay discount-eligible accounts. Collect lien releases for any job where you've received a progress payment.
- Quarterly: Review pricing tiers, open credits, and credit limits. Ask for guarantee removal on accounts that qualify.
If you run a lean operation and your business and personal finances still overlap, keep supplier accounts strictly on the business side. Solo operators and self-employed tradespeople who want help separating the two and tracking where their money goes can look at Stintly, which is built for freelancers and small business finance. Keeping supplier payments, owner draws, and personal spending separate makes tax season much easier.
Your supplier is a business partner, not a bill. The contractor who pays on time, reconciles carefully, and communicates early when a job runs long gets priority on allocation when materials are short, which can matter more than any discount.
Special Case: Repeat Clients and Property Owners
If a lot of your work comes from landlords and property managers doing unit turns, repairs, and make-ready work, supplier terms matter even more. Those jobs are small, frequent, and often billed monthly or on net-30 terms of their own. That can leave you waiting 45–60 days to get paid for materials you bought on net 10th prox.
Two adjustments help. First, match your billing cycle to your supplier cycle: invoice property clients on the 1st so payment lands before your supplier statement is due. Second, keep a separate supplier sub-account for each property owner so you can pass material costs through with clean documentation. Many landlords track repair spending per unit with tools like KeyLoft, and they'll appreciate invoices that line up clearly with their own records. Easy billing gets paid faster. It also helps you get the next turnover job.
TrestleBook handles this kind of work well: set up each property or unit as its own job, log materials as you buy them, and when you invoice, every cost is already sorted and ready to bill through.
Supplier credit isn't exciting, but for most small contractors it's the cheapest working capital they'll ever have. Read the terms, take the discounts when your cash forecast supports it, tie every ticket to a job, and reconcile every statement. Contractors who do those four things consistently keep more of every job, avoid lien problems with clients, and get treated as preferred customers when supply gets tight. Start with this month's statements: reconcile one account fully and see what you find.